BQ AND LUMP SUM CONTRACT28

Lump Sum BQ

1 Consultants

Drawings

Must be detail. Detail schematics

sufficient.

2 Consultant‟s BQ Simple 1 Lot Detail measurements

3 Consultant‟s final

measurements

Just check for VO VO and comparison

between contract

drawings & as-built,

4 Contractors

approach after

award

Do as little as possible

within the interpretation

of the Contract.

Do as much as possible

within the interpretation

of the Contract.

5 Consultant‟s

professional

liability

Drawings not detailed

enough attracts

„negligence torts‟.

Quantities too much

different from actual

quantity attracts

„negligence torts‟.