                            Scope / Objectives.
In the beginning of each project and before casting the retaining wall, we have to Make sure that we already fixed our sleeves for DEWA high voltage cables, Etisalat Cables or for earthling system, officers the size, No and heights of the sleeves as P...
	Area of installation - Interior.
	Enclosure pattern - Flush.
                        
Document Text Contents
Page 1

Al Andalus Tr. & Elect. Cont.

Co. L.L.C


Doc. No.

REV.

Date


JB-GN / ELECTRICAL

0.

JANUARY - 2010


METHOD STATEMENT: ELECTRICAL WORKS

Page 1 of 31

Method Statement Electrical Works






AL ANDALUS TRDG. & ELECT.
CONT. CO. L.L.C



Sharjah – U.A.E.






METHOD STATEMENT


FOR


ELECTRICAL WORKS

Page 2

Al Andalus Tr. & Elect. Cont.

Co. L.L.C


Doc. No.

REV.

Date


JB-GN / ELECTRICAL

0.

JANUARY - 2010


METHOD STATEMENT: ELECTRICAL WORKS

Page 2 of 31

Method Statement Electrical Works




METHOD STATEMENT:
ELECTRICAL


Table of Contents:


1. Scope / Objectives.


2. Activities.


3. Responsibilities.


4. Resource Requirements.


 Material.


- Drawings.


5. Procedure.


6. Testing and Commissioning.


7 Test Report Formats.


8. Manpower.


9. Records.


10. Approvals.

Page 15

Al Andalus Tr. & Elect. Cont.

Co. L.L.C


Doc. No.

REV.

Date


JB-GN / ELECTRICAL

0.

JANUARY - 2010


METHOD STATEMENT: ELECTRICAL WORKS

Page 15 of 31

Method Statement Electrical Works

 1st coat painting should be completed in the Main Electrical Room before the
panels are delivered to site upon the Consultants inspection and approval of the
Panels.



 Cable ladders and cable trays start assembling at main electric room as per the
approved layout for incoming and outgoing cable which is top or bottom entries.


 Incoming and outgoing feeder will be installed.



 Dressing and termination for the feeders will be done by a electrical specialist
and well experienced and professional electricians.


 The Main distribution boards will be identical to the sub-main distribution

boards in all respect except that all equipments and connections will have front
and rear access.


 All the meters (CT’s meter and check meters) will be installed in the respective

main distribution boards after tested and calibrated by DEWA.

Testing:

 On completion of the installation and prior to its being made “Alive” for service,

all the electrical test will carried out all sections of the works in the presence of
the Consultants’ and all the tests will be carried out in compliance with the
DEWA regulations and the contract specifications. All the test reports will be
submitted to the Consultants’ along with the As-built drawings and Operation
and Maintenance documents.


The Test includes the Following:

 Mongering incoming line terminals and buses, phase-to-phase and phase-to-

ground after disconnecting devices sensitive to megger voltage.

 Test ground connections for continuity and resistance.


 Earth continuity and earth resistance tests.


 Mechanical interlocks will be checked for proper operation.


 Unit compartment doors will be adjusted.

Page 16

Al Andalus Tr. & Elect. Cont.

Co. L.L.C


Doc. No.

REV.

Date


JB-GN / ELECTRICAL

0.

JANUARY - 2010


METHOD STATEMENT: ELECTRICAL WORKS

Page 16 of 31

Method Statement Electrical Works


5.12 Fixing wiring accessories, light fittings.

 After finishing the pre-final coat for the building, we will start fixing the wiring

Accessories, light fittings, fire alarm devices. Of course the fitting where is
coming in the false ceiling should be fixed in the proper way with more
supports if required:


Area of installation - Interior.

 Enclosure pattern - Flush.


 Cover plate finish, all accessories to match - Molded plastic, color - white.


 Ear thing terminal integral within switch box.


 Neon indicator with red lens, illuminated in `ON’ position, for connection

units.

 Switch rocker bar color - white.


Area of installation – Exterior/Plant (Pump Room)

 Enclosure pattern - Surface and weatherproof.


 Accessory mounting - Direct to enclosure.


 Earthing terminal integral within switch box.


Installation General.

 All accessories shall be properly aligned with vertical edges; plumb and

horizontal edges level and mounted at the height recommended below and shall
be to the approval of the Engineer.


 All flush accessories shall have cover plates fitted correctly onto the wall or

ceiling or any other services. Any accessories found to be incorrectly aligned
after installation will have to be removed and re fixed.

Page 30

Al Andalus Tr. & Elect. Cont.

Co. L.L.C


Doc. No.

REV.

Date


JB-GN / ELECTRICAL

0.

JANUARY - 2010


METHOD STATEMENT: ELECTRICAL WORKS

Page 30 of 31

Method Statement Electrical Works








TEST REPORT


FOR


ELECTRICAL WORKS

Page 31

Al Andalus Tr. & Elect. Cont.

Co. L.L.C


Doc. No.

REV.

Date


JB-GN / ELECTRICAL

0.

JANUARY - 2010


METHOD STATEMENT: ELECTRICAL WORKS

Page 31 of 31

Method Statement Electrical Works


TEST REPORT FORMATS




1. Distribution Boards and Final Circuits.


2. MDB’s and SMDB’s Motor Control Centers.


3. Power Cables.


4. Earth Electrode Resistance.


5. Fire Alarm System.


6. Intercom System.


7. Low Current System


8. Generator Set